 APPLICATION METHOD

PREPARATION:

  • Concrete needs at least 28 Days to be fully cured.
  • Etch the floor or Grind it.
  • To acid wash, Dilute one third Hydrochloridric acid with water,
  • Add Acid to the water tank,
  • Pour on floor, Use broom to spread it out,
  • Wash it by high pressure washer after 5 Min.
  • Apply PRIMIT when the floor is dried, Use 12 mm nap roller.
  • 4 litre PRIMIT KIT IS ENOUGH FOR NORMAL

DOUBLE GARAGE & NORMAL CONCRETE

  • Follow the ratio, Mix thoroughly by Mixer, Pot life is two hours,
  • Cut edges and corners first.
  • EPOXY PRIMER, Needs to be applied on bare concrete as a thin layer to penetrate and bite the concrete.
  • It needs 8 hours to dry.
  • Inspect the floor, Needs to be fully dried.
  • Patch Cavities and Cracks by Builderpox & Filler blade, Needs 3 hours to dry.
  • ONE 16 Litre KIT,INDOPOX COVERS 80 Sqm ONE COAT.
  • Make it half and apply two coats.
  • Apply First Coat by roller, Use 12 mm nap roller
    • Follow the ratio, Mix Part A & Part B thoroughly by Mixer or Drill Move paddle mixer vertically,
    • Pot life is 30 Minutes, Make sure everything is ready to apply.
    • Tape all skirting and doors to protect from Epoxy Splash.
    • Mix Small Batch, Use Scale, Mix by Weigh not Volume.
    • Start by 5 Kg Part A & 1 Kg Part B
    • Cut edges and corners first by baby roll or brush.
    • Pour on Floor, Use Squeege to spread it out, apply by 270 mm roller, Check not to leave any lines or spot behind.
    • Needs 8 hours to dry and walk on.
    • Interval is between 8 to 72 hours.
  • Apply Second Coat by roller, Use 12 mm nap roller
    • Follow the ratio, Mix thoroughly by Mixer, Pot life 30 Min.
    • Mix Small Batch, Use Scale, Mix by Weigh not Volume.
    • Cut edges and corners first.
    • Pour on Floor, Use Squeege to spread it out, apply by 270 mm roller, Check not to leave any line behind. Needs 24 hours to walk on.
    • Needs 7 days to be fully cured
  • Do not wet the area at least for seven days depends on the weather condition.

Enjoy Your Nice & Gloss Floor